Concept reference
A datum is the agreed zero from which elevations are measured; stationing measures distance along an alignment. Neither changes the physics, but both control whether independent drawings describe the same physical point. Elevation differences survive a datum shift; mismatched datums create fictitious static head and construction conflicts.
If every elevation moves by a constant C, then (z2 + C) − (z1 + C) = z2 − z1. Stationing is commonly written as accumulated length, such as 0+125 for 125 m in a metric project, but notation and reset rules are local drafting practice and must be defined on the sheet.
“Local datum” without a recoverable benchmark can strand future survey work. Confusing pipe invert, crown, centreline and water-surface elevation is equally dangerous because all four may appear at one station but represent different heights.
See §1.5 for drawing literacy and §5.2 for datum errors in energy calculations.
Physics sets the relationships; the owner, manufacturer and governing local standard set the project criteria.